Project

Marine and Rail Terminal Expansion

The design and upgrade of an existing marine terminal to incorporate fuel rail offloading (32 spots), pipeline, bulk tank storage and marine loading at multiple terminals.

Location
British Columbia
Industry
Energy
Client
Confidential
Challenge

Rail Offloading Rack Expansion for Environmental Compliance

Increased the rail offloading rack to 32 railcar positions, allowing 64 railcars to be offloaded per day. Special considerations for environmentally sensitive site located on Canadian Coastal waterways, vapour recovery, marine terminal structural modifications and environmental permitting.

Outcome

Feasibility Studies and EPCM Execution with Safety Excellence

TWD completed FEL-1, FEL-2, FEL-3 feasibility studies and EPCM execution (as agent). Project achieved excellent safety performance.

Result
$180MM
Total installed cost
Up to 64 Railcars/day
The rail offloading rack has been expanded to accommodate 32 railcar positions, enabling the offloading of up to 64 railcars per day.
Turnkey Project
TWD completed FEL-1, FEL-2, FEL-3 feasibility studies and EPCM execution.